Multiple Single Phase Setup Guide
This is a summary guide of the important steps to set, while configuring the Eniscope and admin.eniscope.com for a multiple single phase system.
You will find a full installation guide at: https://help.bestsupportdesk.com/solution/articles/4000119067-first-eniscope-installation-2018-
For the Eniscope installation and setup.
And a detailed quick start guide on the Admin.eniscope.com settings at: https://help.bestsupportdesk.com/solution/folders/4000002565
Physical installation
If you are setting up multiple single phases to one Eniscope Input (which can support 3 CTs), then when you set up the data view, you'll need to add a separate dataview for each phase in turn, by selecting a different CT.
Eniscope Hub settings
For the Eniscope Hub, you only need to set the Meter 'Phase Configuration' to 3 phase during setup.
Admin.eniscope.com
Add Equipment
Although only for reference, we recommend you fill in the advanced configuration box, by selecting 3 Phase.
Add Dataview
For the dataview in the multiple single phase setup, you need to select the 'CT1' option. Then repeat for CT2 and CT3 (so you have 3 dataviews for 3 single phases).
You now have all the important settings for a multiple single phase.
Analytics
In Analytics, you should select the System for 'phase type' on the options tab. Then continue to select the meters, parameters and time interval of interest.